  • Difficulties in Moving Plant Location
    • 담당부서 : 외투기업고충처리실(고상원)
    • 조회수 : 1,948
  • Organization : WHO, KFDA, FDA
  • Regulation : administrative management
Grievance
Grievance
Problems of moving plant sites rose as the railways and light rail transit under the city development plan were to pass through a part of the plant sites of a foreign-invested company.

The city concerned had requested that the foreign company move its plant facilities by the end of 2008, yet it would have taken four to five years to move the plants and recommence manufacturing its products (much time would be needed for the plant construction due to the characteristics of the biomedical products which require verification, approval and registration processes with the WHO, KFDA, FDA, etc.).

Resoultion and Results
Resolution and Results
A request was made to the city concerned to make an adjustment to its enforcement of the city development project to allow the filing foreign company to carry on its manufacturing activities till the end of 2010.

Outcome:
The filing company’s request to postpone the due date for moving the plants was accepted by the concerned city.