  • Delays in land adjudication regarding office building
    • 담당부서 : 외투기업고충처리실(고상원)
    • 조회수 : 1,480
  • Organization : Investment Promotion Division, Gyeonggi Provincial Government
  • Regulation : Act on Acquisition of and Compensation for Land, etc. for Public Works
Grievance

(Background) A company has expanded its business to Icheon and their new office building is in its completion stage, ready to secure roads and formulate a district unit plan. However, the company has applied for adjudication as the landowner has opposed to the use of the land.

 

(Main issue) Although the competent organization is delaying the procedure due to the large number of adjudication applications, request for prompt assessment of the case is necessary as the company plans to move into the new office building no later than March 2017.

Resoultion and Results

(Resolution) We submitted our request for prompt assessment of the company’s adjudication application to the competent Land Tribunal.

 

(Result) Decisions have been made to accelerate the process and complete the adjudication by this year through coordinated effort with the relevant local government.